4.8 Google reviewsoffice@macdonaldcrane.comMost weeks book up. Call two or three days ahead.

Generator Crane Lifting and Setting for Contractors Across Southeastern Massachusetts, Boston, Cape Cod, Rhode Island & Southern New Hampshire

  • Generator sets placed on prepared foundations
  • Operators certified for mobile crane work
  • Easton-based since 2009

Request a Lift Quote

The Pad Is Poured Where the Wire Runs

A generator pad goes where the electrical run is shortest, not where a crane can work. So by the time the set arrives on a flatbed, getting it onto that pad depends on whatever room the site has left for a crane. Your crew stands by and the job waits until the set is bolted down.

At MacDonald Crane we lift generator sets onto their pads for electrical contractors and facilities teams. A lot of it is behind buildings that are open and running. Some is new construction, and some is a replacement going into a spot nobody planned for a crane.

The first thing we want to know is how far the pad sits from the nearest place a crane can set up. That distance is one of the main factors that determines the crane setup and lift requirements.

That measurement rarely exists this early, and it does not need to. Send us a photograph of the pad and anywhere a crane could park, and we will work the lift out with you first.

A MacDonald Crane boom truck lifting an enclosed generator set off a flatbed, its new pad formed up in the foreground

How Do You Size a Crane for a Generator Set?

Kilowatts will not tell you what a generator weighs. A 100 kW rating describes the power the set puts out, not its weight. Two sets with the same rating can be thousands of pounds apart once the enclosure and tank are counted.

Call (508) 238-1055

The Cranes That Set Them

The machine choice depends on the weight, height, distance to the pad and available setup area.

The Manitex 30100C 30-ton boom truck with its boom raised beside a commercial building

Manitex 30100C · 30-Ton Boom Truck Crane

Most sets go out on this one. It carries a 100-foot main boom in four sections, and it fits into side yards and courtyards where the pad sits close to the building.

See the 30-ton boom truck crane
The Manitex 50128S 50-ton boom truck with its boom raised

Manitex 50128S · 50-Ton Boom Truck Crane

This one goes out when the job needs more capacity and reach. Its main boom runs to 128 feet in four sections. Sets going onto a roof are the usual reason for it.

See the 50-ton boom truck crane

Three Numbers Decide the Pick

A MacDonald Crane boom truck with its boom raised beside a multi-storey building

What the set weighs, enclosed and on its tank. Send the figure for the set as it will arrive, not the open skid. One 100 kW diesel set is listed at about 2,800 lbs open with no tank, and about 5,700 lbs enclosed on its sub-base fuel tank.

The height it has to clear. Most sets land on a pad at grade, so what we want is the height of whatever the load travels over. Usually that is a fence, a screen wall or the building itself, though a set going onto a roof changes the machine.

How far the pad is from where the crane can set up. Pace that distance from the nearest firm, level ground a crane could sit on to the middle of the pad. If a transformer, a loading dock or parked cars are in the way, say so.

Those three numbers help determine the right crane and what the lift will require.

Give Us the Three Numbers Before the Pad Is Poured

Those three numbers tell us which machine the set takes and how the day should run. They also show whether anything about the pick wants looking at first.

  • Generator weight

  • Height it must clear

  • Distance from where the crane can set up

No weight yet? Send a photograph of the nameplate and one of the pad, and we can work from those. Or call (508) 238-1055.

Send It Over

The Proof Behind a Generator Lift

2009the year the yard in Easton opened, with one crane
9 in 10of what we book is a contractor calling us again
1 dayone business day is all a certificate of insurance takes
NCCERcertifies our operators for mobile crane work, ANAB-accredited

What Happens on the Day the Set Lands?

  1. Before the date.

    You give us the weight off the nameplate, the height it clears and the distance to the pad. We name the machine and how long the pick should run.

  2. Setting up.

    The operator walks the site with you, then sets the crane on firm ground with pads under the outriggers. On a tight site, settling that spot takes longer than the lift.

  3. The pick.

    The set comes off the flatbed and travels the path the operator walked. Your crew takes it at the pad, and the anchor bolts get checked before it comes down.

  4. Landing it.

    It lands slowly onto the bolts, with your electrician calling the last few inches. Once it is shimmed or bolted down, the crane packs down and takes the rigging with it.

What the Pad Needs Before the Crane Arrives

We bring

  • The operator, certified through NCCER for mobile crane work
  • Rigging sized for the set, slings and shackles included
  • Pads and cribbing under the outriggers
  • A certificate of insurance, inside one business day if you need it

You arrange

  • The pad poured, cured and the anchor bolts set where the drawings put them
  • Somewhere firm and level for the crane, and the way in kept open
  • Your electrician or millwright on site to receive it and bolt it down
  • Any street permit, and the police detail if the crane sits on the road

Those last two are not ours. We do not pull permits and we do not book police details, and that sits with whoever schedules the job. Apply as soon as the date looks likely.

A MacDonald Crane boom truck with its outriggers down on pads beside a building

4 Reasons Contractors Send Us Their Generator Sets

We Look at the Pad First

Send the pad location while it is still a mark on a drawing and we will say whether a crane can reach it. Moving a pad on a drawing costs nothing. Moving one after the concrete is down is a different job.

We Work From the Real Weight

The weight that matters is the set as it ships, enclosure and fuel tank included. That figure is on the nameplate rather than the quote. Send a photograph of that plate and the crane gets sized against the set that actually arrives.

The Set Lands on the Bolts

A generator comes down onto anchor bolts already set in the concrete. There is no sliding it across afterwards. The operator brings it down in inches while your electrician lines it up, and that last part of the pick is where the time goes.

We Have Set 15,000 Pounds

One of the sets we are proudest of went 15,000 lbs onto its pad. A standby unit for an office building, a school or a small plant is ordinary work. The weight is rarely the part that decides the day.

What Drives the Cost of a Generator Lift?

Four things fill the hours. The first two are getting the crane into position and the distance to the pad. The third is how long the set takes to land on its bolts, and the fourth is the drive, which runs port to port from Easton. A set on open ground is a short morning. The same set in a courtyard is not.

You control the approach and the pad. Clear whatever is parked nearby, have the bolts in and your electrician there, and the crane is not idle.

A load lifted over power lines by a MacDonald Crane boom truck What each crane costs per hour, and the minimum it books at

Where You Can Find Our Cranes

Based in Easton, MacDonald Crane serves contractors across Southeastern Massachusetts and surrounding areas.

Full service area
  • Norfolk County
  • Braintree
  • Canton
  • Dedham
  • Foxborough
  • Quincy
  • Sharon
  • Stoughton
  • Walpole
  • Suffolk County
  • Boston
  • Chelsea
  • Revere
  • Winthrop
  • Worcester County
  • Auburn
  • Milford
  • Northborough
  • Shrewsbury
  • Westborough
  • Worcester

FAQs

Can you set a generator on a rooftop?

Yes, and reach matters more on a roof than anywhere else. Send the roof height and where on the roof it has to land.

Do you take the old generator away?

We can lift it out and set it on whatever is taking it away. Hauling it off site is a separate conversation. Tell us on the first call.

How much notice do you need to book?

Advance notice helps us review the setup and schedule the right equipment. Call earlier if the pad is somewhere awkward, and we can work the setup out first.

Will the crane fit down beside the building?

Often, and a photograph answers it faster than a measurement. Send one from the street looking in, and one from the pad looking out.

What is the heaviest set you can lift?

That depends on how far the crane has to reach. Send the weight and the distance to the pad for a straight answer.

Google Reviews

What Our Customers Say

4.8 Google reviews
  • Google review

    As the CFO of Climate Design Systems & Merrimack Valley Corporation, MacDonald Crane has been a very reliable partner to us and has always come through. Their prices are very competative to other local crane companies and they deliver! I highly recommend.

    Keith Bentley, Google reviewerKeith BentleyGoogle reviewRead on Google
  • Google review

    10 years ago they delivered and placed four rooftop units to my job site. They were punctual, professional and the driver was a hot ticket. Will definitely use them again.

    Gary Vitagliano, Google reviewerGary VitaglianoGoogle reviewRead on Google
  • Google review

    Very reliable & safety is their #1 concern

    Cheryl O'Donnell, Google reviewerCheryl O'DonnellGoogle reviewRead on Google
  • Google review

    I have a hot tub business and use MacDonald exclusively for crane service. Best around!

    Roger Mayer, Google reviewerRoger MayerGoogle reviewRead on Google

Get the Right Crane to Your Pad

The pad is where the electrical run put it, and the only question left is whether a crane can reach it. Send the weight, what it has to travel over, and how far the pad sits from the nearest ground a crane can stand on. You will have your answer and your machine.

Call (508) 238-1055